2019-03-01 Dematic Recurring Meeting notes
Date
Mar 1, 2019
Participants
@Cynthia Schwarz (Unlicensed)
@David Lacy
@Chin U. Kim
Adam Ferrero
Paul Smith
@Justin H. Hill
@John Oram
@Margery Sly (Unlicensed)
Kevin Hirth
Gautam Badhuri
Goals
Workstation Setup Process
Cables - will need both 15 ft displayport and longer power cables
Server Configuration
SRM connection - Gautam was successful in controlling the SRMs remotely
Configuring access between Alma and prod servers
Security
Sent list of permissions/roles to Gautam on 2/28
End-to-end testing
Scheduled for Mini loads on 3/8
Scheduled for Unit loads on 3/12
Timeline review
Discussion topics
Notes |
---|
Workstation Setup
Server
Security
End-to-end testing
Timeline3/8: End-to-end testing simulation for Mini Loads 3/12: End-to-end testing simulation for Unit Loads and review of record display for unit load items 3/15
3/18: Deliver workstations to Charles 3/19: Install workstations in Charles - both unit load and mini loads 3/20-22: Gautam can test the connections between the pick stations and the servers 3/25
3/26 - 3/29: Test load of physical materials both into ML and UL 4/1
4/2: Operational training - mini loads 4/3: operational training - unit loads 4/4: End-to-end testing of the ML 4/5: End-to-end testing of the UL 4/9 - 4/11: Maintenance training on the Mini Load aisles 4/12: Make up maintenance training on Unit Load 5/9: Begin Alma record load to EMS 5/13??: Start loading ASRS |