2019-02-13 Dematic Recurring Meeting notes

2019-02-13 Dematic Recurring Meeting notes

Date

Feb 15, 2019

Participants

  • @Cynthia Schwarz (Unlicensed)

  • Gautam Bhaduri

  • David Lacy

  • Nancy Turner

  • Chin Kim

  • Larry Brandolph

  • Bill Barnes

  • Holly Tomren

  • Kevin Hirth

Skype Link: https://meet.lync.com/dematic0-dematic/gautam.bhaduri/5WB779GB

Goals

  • Server installation status

  • Workstation setup status

  • Gautam’s visit 3/4-3/8 and 3/11-3/15

    • Operational training

    • Test load

    • Test load testing

  • Clarify the Dematic Sprocket setup - I received an invitation to schedule an initial meeting

Discussion topics

Notes

Notes

Server Installation Status

  • Server installation is done!

  • Cal turned over to Gautam this morning

  • Gautam has been installing the software, but having trouble starting the software

Workstation Setup

  • Waiting for the six service accounts for the autologin to be setup

  • EMS control center is installed - only installed on one computer so far

  • Set up the browser to only allow Alma

  • Next steps: Chin and Gautam will schedule time to discuss early next week

  • Cabling

    • Between monitor and tower

      • Displayport connection - Gautam will order

      • Needs to be 10 ft

    • Power cables for monitor and workstation

      • Current monitor cable is 3 feet

      • Current tower cable is 4 feet

      • Bill and Larry will scope out pick station setup to see best place to mount a electrical box and follow up

Gautam’s visit 3/25 - 4/5

  • Operational training - April 2, 3

  • Test load if possible in the first week

  • We should be able to have workstation installed prior to the visit

Sprocket CMMS Software

  • Who: people who are maintaining equipment and spare parts

  • Facilities people from who are attending the training

  • Cynthia will coordinate this first meeting

Spare parts

  • they have been arriving and are being stored in our off-site storage in Kardon

  • by end of May, we could start loading parts into the building

SQL Scripts for the remaining items

  • send them to Gautam in small batches

  • as Chad gets them and transforms them, go ahead and send to Gautam

Timeline

2/19 - 2/21: Maintenance training on Unit Load aisle

3/15: Deadline for having the ASRS mezzanine painted and floors sealed and space locked

Week of 3/18

  • Set up all workstations

  • Deliver all test load items to Charles and store on ASRS mezzanine

3/25 - 3/29

  • Gautam will be on site

  • We will do the test load this week

4/1 - 4/5

  • Test load for both mini load and the unit load scheduled for 4/4 and 4/5

  • Gautam will be on site

  • Operational training scheduled for 4/2 and 4/3

4/9 - 4/11: Maintenance training on the Mini Load aisles

5/9: Begin Alma record load to ASRS

5/20??: Start loading ASRS

6/1: Move spare parts to ASRS chamber.

Next meeting: Friday, February 22 at 1pm

Action items

@Chin U. Kim and Gautam will meet early next week to discuss next steps for workstations
Gautam will order 10ft displayport cables for connection between monitor and tower
Larry and Bill will scope ideal location for electricity in the pick stations and report back

Decisions