2016-12-02 ExLibris Sales to Service Meeting notes

Date

Attendees

Goals

Discussion items

TimeItemWhoNotes
HIgh-level overviewTony
  • Tony is first point of content - Program manager
  • work between project signing and kickoff - the "getting ready" period
  • Confirm actual dates and review documentation
  • Kickoff: Tony will transition responsibility to project team
    • Project Manager
    • Alma Consultant
    • Primo Consultant
  • Go LIve: project will continue for about a month before switch to support

Kick-off Meeting
  • Allocate 2 hours
  • Web-based meeting
  • Review project schedule and many more details
  • Meet the project team
  More details Tony
  •  We don't have a slot available to go live at the end of June. Would have to wait until the end of July.
  • Test load slot in February - ideal to start in December.
  • ExL has a global migration calendar of all customers migrating to Alma - have to reserve the correct slot on that global calendar.
  • Regardless of Go-Live date, we'll still start in December
  • Two test loads: build first test load in February and access in March
  • Looking for Kick-off on December 12.
  • Will be actively working on pre-implementation even after the kick-off meeting.
  • After today's call, we'll have a workbook to complete in order to get the timeline set.
  • Send questions to Tony
  • Schedule meeting with Project team before the kick-off


Action items

  • Tony will double check about the Go-Live date and make sure that we can do it end of June instead of end of July - check with Melissa 
  • Tony will send the Alma/Primo Implementation Workbook
  • Cynthia will go through the workbook
  • Cynthia will send list of questions to Tony
  • Cynthia will schedule pre-kickoff meeting - Tuesday 12/6 12:30 - 2pm
  • Cynthia Send best times for Kick-off meeting to Tony