Time | Item | Who | Notes |
---|
| HIgh-level overview | Tony | - Tony is first point of content - Program manager
- work between project signing and kickoff - the "getting ready" period
- Confirm actual dates and review documentation
- Kickoff: Tony will transition responsibility to project team
- Project Manager
- Alma Consultant
- Primo Consultant
- Go LIve: project will continue for about a month before switch to support
|
| Kick-off Meeting |
| - Allocate 2 hours
- Web-based meeting
- Review project schedule and many more details
- Meet the project team
|
| More details | Tony | - We don't have a slot available to go live at the end of June. Would have to wait until the end of July.
- Test load slot in February - ideal to start in December.
- ExL has a global migration calendar of all customers migrating to Alma - have to reserve the correct slot on that global calendar.
- Regardless of Go-Live date, we'll still start in December
- Two test loads: build first test load in February and access in March
- Looking for Kick-off on December 12.
- Will be actively working on pre-implementation even after the kick-off meeting.
- After today's call, we'll have a workbook to complete in order to get the timeline set.
- Send questions to Tony
- Schedule meeting with Project team before the kick-off
|