- The plan- soft launch in fall, migrate to hosted instance in spring
- LTD can't support a locally hosted dspace long term
Questions Questions...
How does the state of the Elements project affect this decision?
...
Is it worth looking at other options since we're at this point?
- We
- Dspace will allow the project to move more quickly; the repo we have can be populated starting in the summer, and the vendor can do the migration work as a part of the contract
...
Question- how are we going to frame the soft launch to faculty, library staff
- Is it a 'beta'?
GG to do...
Fully Gabe Galson will fully scope login/authentication options, confirm what is needed with Annie and Alicia
Annie Johnson (Unlicensed) and the services group will Advisory text on the beta launch will be drafted. The group will think about how to communicate with the wider community about the soft launch.
Decision: no DOIs in the interim system