Notes |
---|
Server Installation Status
Workstation Setup
Gautam’s visit 3/25 - 4/5
Sprocket CMMS Software
Spare parts
SQL Scripts for the remaining items
Timeline2/19 - 2/21: Maintenance training on Unit Load aisle 3/15: Deadline for having the ASRS mezzanine painted and floors sealed and space locked Week of 3/18
3/25 - 3/29
4/1 - 4/5
4/9 - 4/11: Maintenance training on the Mini Load aisles 5/9: Begin Alma record load to ASRS 5/20??: Start loading ASRS 6/1: Move spare parts to ASRS chamber. Next meeting: Friday, February 22 at 1pm |
Action items
- Chin U. Kim and Gautam will meet early next week to discuss next steps for workstations
- Gautam will order 10ft displayport cables for connection between monitor and tower
- Larry and Bill will scope ideal location for electricity in the pick stations and report back
...